The construction work has continued after the Covid-19 Level 5 lockdown was lifted. The completion date of the project has been affected by the Covid-19 pandemic and is currently expected in September 2021.
Work is currently underway in Cogmanskloof, Montagu, and Ashton. The Ashton Bridge construction, specifically the attachment of the steel cables between the arch and the deck tiebeam, is progressing well.
Since the previous report, the contractor has completed the following activities:
The contractor is currently busy with the following activities:
Work | Estimated Completion |
The construction of road layers on the Ashton LHS from km 17 to 17.6. | December |
The construction of two parking areas in Ashton. | December |
The installation of services and stormwater pipes in the west-bound lane (RHS) in Ashton from Loop St to Station Rd. | July |
Construction of a service culvert for Langeberg & Ashton Foods near Platform 62. | July |
The installation of watermains through the Cogmanskloof River, as part of the re-alignment of pipelines around the new Ashton Bridge footprint. | July |
The construction of road layerworks at the Swellendam intersection | August |
The construction of road layerworks in Cogmanskloof. | December |
The construction of the sidewalks in Montagu. | August |
Construction of leiwater structures in Montagu. | August |
Stripping of falsework from the Ashton Bridge. | September |
Preparation for the traffic diversion onto the new Ashton Bridge in its temporary position. | August |
Various ancillary works, including sidewalks in Ashton, stone masonry walls in Cogmanskloof, landscape rehabilitation in Cogmanskloof, stormwater structures (pipes, inlets & outlets, concrete sidedrains, down chutes, erosion protection etc.) in Cogmanskloof, testing ofservices sleeves, building of service manholes throughout the project etc. |
September 2021 |
The contractor has reported that the following activities will commence during the next three months:
This construction project has created direct work opportunities for over 270 people from the Western Cape. The cumulative man-days worked by people from the local community (Ashton, Zolani, Montagu, and Ashbury) is over 35 000, resulting in a substantial amount paid in wages to the local community.
Jandre Bakker
Head of Communication
Department of Transport and Public Works
Email: Jandre.Bakker@westerncape.gov.za