Gouritsmond Road reopened
Divisional Road 1525 (Gouritsmond Road) has been reopened to traffic following extensive repairs.
- During the flood significant damage was caused including a 90m section of the Eastern Approach with erosion up to 5m deep in some areas.
- Approximately 3 000 cubic meters rockfill and bulk material had to be used during June 2026.
- Base course layers were reinstated by early July.
- By mid-July 2026 the priming was completed.
- The seal is being applied but the road can be reopened during this stage.
- We thank our teams and partners for their tireless work. Yet another important route reopened.
Please use the road with caution as works continue with road marking, danger plate installation, etc.