I am deeply concerned with the continued delay of the Qolweni Phase 3A Housing project in the Bitou Municipal area.
The Western Cape Government has consistently offered to assist the municipality should they be unable to commence with this project. Regrettably, unless a formal request is received from Council for the Western Cape Department of Human Settlements (WCDoHS) to take over this project, we’re not able to do so.
This project, which has a budget allocation of R 33, 5 million for construction and professional fees, was approved in October 2019. Construction of 169 units had to commence in January 2021.
The facts in this matter are:
It must also be stated that the contractor has sought to interdict the WCDoHS and / the municipality from appointing a new contractor to complete the works. Even though Ukhana has taken this matter to the court, the WCDoHS has not received any papers to this effect.
My appeal to all parties is to remain calm and to find a speedy resolution to this matter. I call on community members to continue engaging their municipal officials. In due course I will also be visiting the area for various engagements on this matter.
As the WCDoHS, we remain committed to this project and sufficient funding has been set aside – but the responsibility lies with the Municipality to complete the project – unless it is officially handed over to us.
Marcellino Martin
Spokesperson for Minister Tertius Simmers
Marcellino.Martin@westerncape.gov.za
021 483 3397 (o)
082 721 3362 (m)
Or
Nathan Adriaanse
Director Communication & Stakeholder Relations
Tell: 021 483 2868
Mobile: 083 2631720
Email: Nathan.Adriaanse@westerncape.gov.za