Shut-down plan:
The roads included on this project where works have commenced, will be made safe over the December embargo period with temporary line marking.
These roads will be marked as per the details listed in the table below:
Road | Stake Value (km) |
Current Treatment |
Road Marking | Road Studs |
TR88/1 | 60.34 – 70.2 | Texture slurry | Temporary overtaking lines |
None |
TR1/3 | 0 – 16.6 | Armour seal on base patches |
Heavy pre-marking | Temporary road studs at 24m spacing |
MR401 | 0.0 – 9.8 | Texture slurry | Temporary nonovertaking line |
Temporary road studs at 24m spacing |
Responsible Persons:
The following personnel will be on site and available in case of emergencies, on the
dates indicated in the table below:
Name | Responsibility | Dates | Contact Number |
Simon | Site Reliever | 14 Dec – 28 Dec | 073 224 3144 |
Adrian | Site Reliever | 28 Dec – 7 Jan | 073 090 0701 |
Nuraan | In case of emergency | December Standby | 082 702 6581/ 079 603 3916 |
Mr Malgas | In case of emergency | January Standby | 083 306 6718/ 071 030 9511 |
Jandré Bakker
Head of Communication
Department of Transport and Public Works
Email: Jandre.Bakker@westerncape.gov.za
Sound bites can be requested via Whatsapp on 083 310 5357.