Shut-down plan:

The roads included on this project where works have commenced, will be made safe over the December embargo period with temporary line marking.

These roads will be marked as per the details listed in the table below:

Road Stake Value
(km)
Current
Treatment
Road Marking Road Studs
TR88/1 60.34 – 70.2 Texture slurry Temporary overtaking
lines
None
TR1/3 0 – 16.6 Armour seal on
base patches
Heavy pre-marking Temporary road
studs at 24m spacing
MR401 0.0 – 9.8 Texture slurry Temporary nonovertaking
line
Temporary road
studs at 24m spacing

 

Responsible Persons:
The following personnel will be on site and available in case of emergencies, on the
dates indicated in the table below:

Name Responsibility Dates Contact Number
Simon Site Reliever 14 Dec – 28 Dec 073 224 3144
Adrian Site Reliever 28 Dec – 7 Jan 073 090 0701
Nuraan In case of emergency December Standby 082 702 6581/
079 603 3916
Mr Malgas In case of emergency January Standby 083 306 6718/
071 030 9511


Emergency Numbers:

  • Police: 044 752 6600 / 10111
  • Ambulance: 044 752 1114 / 10111
  • Fire Brigade: 044 805 5171 / 10111
Media Enquiries: 

Jandré Bakker
Head of Communication
Department of Transport and Public Works
Email: Jandre.Bakker@westerncape.gov.za
Sound bites can be requested via Whatsapp on 083 310 5357.