Progress Report: Victoria Road Repair and Resurfacing | Western Cape Government

News

Progress Report: Victoria Road Repair and Resurfacing

2 March 2015

Project Description

C958.04: Repair and Resurfacing of Victoria Road (MR103) Km 2.1 to Km 4.75, Near Llandudno

Construction Progress

Eighty-four percent (84%) of the value of the work has been completed. This includes the complete resurfacing of the roadway. Most of the centreline road marking has been completed and the shoulder lines and the quite complex island marking near the Llandudno turnoff will be tackled this week. Strong wind can delay this operation as it tends to blow the paint around. The Contractor will not be on site at all on Friday so as to give visitors and cyclists full use of the roadway. Last Friday an inspection of the roadway way was carried out with the organiser of the Cape Town Cycle Tour and he was satisfied with the condition of the roadway.

Possible Delays

  • Weather.
  • Wind that could delay road marking.

Road and Access Closures

The road marking will not necessitate any stop/go road closures as it can be done with either shoulder closures and/or lane shifts, all clearly marked with delineators. Once again, the delineators being used to define the temporary carriageways have had the positive effect of slowing traffic down. Nevertheless, speeding vehicles are still an ongoing concern. Weather permitting, the road marking could be 100% complete by the end of Thursday. The Cape Town Cycle Tour organiser stated that should it not be complete it would not pose any problems for the cyclists. Tidying up of surplus premix, the removal of stones from the roadway and general tidying up along the roadway will continue this week.

The placing of road studs (cats eyes), the lining of defective storm water pipes under the road, the replacing of damaged poles and the realigning of bad sections of the guardrails and work at the slip repair near the Llandudno turnoff will continue until the end of April.

General Traffic Accommodation

The following is the programme for the week:

  • Monday - 02 March: Completion of the centreline road marking and the island marking near the Llandudno turnoff: centreline closure with one lane of traffic on either side.
  • Tuesday - 03 March: Painting of the southbound shoulder line: shoulder closure with lane shifts accommodating two-way traffic.
  • Wednesday - 04 March: Completion of painting of the southbound shoulder line and starting of painting of the northbound shoulder line: shoulder closure with lane shifts accommodating two way traffic.
  • Thursday - 05 March: Completion of painting of the northbound shoulder line: shoulder line closure with lane shifts accommodating two way traffic.
  • Friday - 06 March: Contractor not on site at all.

Interesting Facts

The road marking on this project will use approximately 600 litres of paint and 720 kg of tiny reflective glass beads (the size of grains of fine salt) that are placed onto the paint whilst it is still wet in order to make it more reflective.

Contact Numbers

General Enquiries: 082 458 7442

Media Enquiries: 

Al-Ameen Kafaar
Head of Communication
Department of Transport and Public Works
Tel: 021 483 9653
Cell: 083 383 3317
E-mail: Al-Ameen.Kafaar@westerncape.gov.za

You can follow the Department of Transport and Public Works on Twitter: @WCGovTPW